The purpose of this assignment it to identify project scope and develop an IT project schedule. You will use Microsoft Project and Excel to complete this assignment. Refer to Appendix A in the textbook for guidance in using Microsoft Project.


Part 1

Complete the “Work Breakdown Structure Template” using the information from the project charter and other relevant information from the Chapter 4 “Running Case.” Break the work down to Level 3 or Level 4, as appropriate for the project. Review Figure 5-3, Figure 5-4, and Table 5-4 from Chapter 5 of the textbook as a guide. Complete the “Work Breakdown Structure Template.”

Enter the work breakdown structure (WBS) in Microsoft Project by creating a new Microsoft Project file titled “Global Treps Project Rev 0.”


Part 2

1. Use the “Global Treps Project Tasks” template to create the work breakdown structure for the new Microsoft Project file, then save as Rev 1 for the assignment.

2. Use the “Global Treps Project Durations Template” to compute the program evaluation review technique (PERT) weighted average durations (in days) for the lowest level tasks for the Global Treps project. Round answers to the nearest whole number.

3. Edit the Microsoft Project file and call it “Global Treps Project Rev 1.” Manually enter the PERT weighted average durations you calculated into the “Duration” field in the Microsoft Project file. Do not copy and paste this information from the “Global Treps Project Durations Template” file.

4. Assume that you have previously met with your team to identify the immediate predecessors for each lowest level task and that this information has been recorded in the “Global Treps Project Predecessor Template.” Using the information in the “Global Treps Project Predecessor Template,” assign the required predecessors to each lower level task in the “Global Treps Project Rev 1” Microsoft Project file. Note that every lowest level task, with the exception of the first task, should have a predecessor and a successor, with the exception of the last task.

5. Ensure that “Summary” tasks (bold tasks) do not have predecessors or successors assigned to them.

6. In the Microsoft Project “Global Treps Project Rev 1” file, indicate the critical path for the Global Treps Project.

7. Submit the “Work Breakdown Structure Template,” “Global Treps Project Durations Template,” the “Global Treps Project Rev 0,” and “Global Treps Project Rev 1” Microsoft Project files.


General Requirements

Prepare this assignment according to the guidelines found in the APA Style Guide, located in the Student Success Center.  .

Templates attached.

Initiating

Finalize project team

Develop project charter

Planning

Develop scope statement

Develop and refine other plans

Executing

Concept
Conduct research for income mechanism into Global Treps
Evaluate current systems

Define requirements

Define user requirements

Define content requirements

Define system requirements

Define server owner requirements

Define specific functionality

Define risks and risk management approach

Develop project plan

Brief web development team

Web Site Design
Create templates and guidelines for running events

Design donation portal for potential investors

Design a submission page for new ideas on products/services

Design registration for organizations to develop custom websites

Design tracking system

Design incentive system

Web Site Development
Develop donation portal for potential investors

Develop a submission page for new ideas on products/services

Develop a registration page for organizations to develop custom websites

Develop tracking system

Develop incentive system

Upload templates and guidelines

Conduct Verification Testing

Conduct Validation Testing

Conduct Pilot Testing

Roll Out
Hold Four Events (in different countries) to Test Site Functionality

Obtain Feedback

Implement Changes

Move site to production server

Determine roll out schedule

Communicate roll out plan to users
Conduct user training

Deploy system

Support
Determine what support resources are needed

Make appropriate staffing changes

Determine method that users will attain support

Determine support process

Launch support

Controlling

Hold formal customer review

Closing

Prepare final report and presentation

Deliver final report and presentation

Durations Template

Task Optimistic Duration (days) Most Likely Duration (days) Pessimistic Duration (days) PERT Weighted Average Duration (days)
Initiating
Finalize project team 2 4 10
Develop project charter 2 3 13
Planning
Develop scope statement 4 8 14
Develop and refine other plans 10 20 29
Executing
Concept
Conduct research for income mechanism into Global Treps 10 20 30
Evaluate current systems 2 4 10
Define requirements 4 16 22
Define user requirements 8 10 23
Define content requirements 4 16 29
Define system requirements 7 17 33
Define server owner requirements 4 18 20
Define specific functionality 10 20 33
Define risks and risk management approach 7 13 21
Develop project plan 9 18 32
Brief web development team 1 1 2
Web Site Design
Create templates and guidelines for running events 4 16 22
Design donation portal for potential investors 7 19 33
Design a submission page for new ideas on products/services 8 10 27
Design registration for organizations to develop custom websites 8 10 22
Design tracking system 5 8 16
Design incentive system 10 15 22
Web Site Development
Develop donation portal for potential investors 9 22 32
Develop a submission page for new ideas on products/services 12 21 37
Develop a registration page for organizations to develop custom websites 12 21 37
Develop tracking system 5 17 21
Develop incentive system 5 17 21
Upload templates and guidelines 2 4 8
Conduct Verification Testing 9 18 27
Conduct Validation Testing 4 15 20
Conduct Pilot Testing 2 3 9
Roll Out
Hold Four Events (in different countries) to Test Site Functionality 24 40 80
Obtain Feedback 2 3 5
Implement Changes 6 11 20
Move site to production server 2 4 6
Determine roll out schedule 2 6 10
Communicate roll out plan to users 2 4 8
Conduct user training 2 4 12
Deploy system 1 1 2
Support
Determine what support resources are needed 2 3 4
Make appropriate staffing changes 2 3 4
Determine method that users will attain support 2 3 5
Determine support process 2 5 11
Launch support 1 1 2
Controlling
Hold formal customer review 1 1 2
Closing
Prepare final report and presentation 2 5 10
Deliver final report and presentation 1 1 2

Work Breakdown Structure Template

Directions: Complete the template using information from the project charter. Break the work down to Level 3 or Level 4, as appropriate for the project.

Project Name:

1.0 Main Category 1

1.1 Subcategory

1.2 Subcategory

1.2.1 Sub-subcategory

1.2.2 Sub-subcategory

1.3 Subcategory

1.4 Subcategory

2.0 Main Category 2

2.1 Subcategory

2.2 Subcategory

2.2.1 Sub-subcategory

2.2.2 Sub-subcategory

2.3 Subcategory

2.4 Subcategory

3.0 Main Category 3

3.1 Subcategory

3.2 Subcategory

3.2.1 Sub-subcategory

3.2.2 Sub-subcategory

3.3 Subcategory

3.4 Subcategory

4.0 Main Category 4

4.1 Subcategory

4.2 Subcategory

4.2.1 Sub-subcategory

4.2.2 Sub-subcategory

4.3 Subcategory

4.4 Subcategory

© 2022. Grand Canyon University. All Rights Reserved.

2

Lowest Level Tasks Immediate Predecessor(s)
Develop project charter Finalize project team
Develop scope statement Develop project charter
Develop and refine other plans Develop scope statement
Conduct research for income mechanism into Global Treps Develop scope statement
Evaluate current systems Develop scope statement
Define requirements Develop scope statement, Evaluate current systems
Define user requirements Define requirements
Define content requirements Define requirements
Define system requirements Define content requirements
Define server owner requirements Define system requirements
Define specific functionality Define user requirements, Define content requirements
Define risks and risk management approach Evaluate current systems
Develop project plan Develop and refine other plans, Define risks and risk management approach, Define specific functionality
Brief web development team Define server owner requirements, Develop project plan
Create templates and guidelines for running events Develop project plan
Design donation portal for potential investors Develop project plan
Design a submission page for new ideas on products/services Develop project plan
Design registration for organizations to develop custom websites Develop project plan
Design tracking system Develop project plan
Design incentive system Develop project plan
Develop donation portal for potential investors Design donation portal for potential investors
Develop a submission page for new ideas on products/services Design a submission page for new ideas on products/services
Develop a registration page for organizations to develop custom websites Design registration for organizations to develop custom websites
Develop tracking system Design tracking system
Develop incentive system Design incentive system
Upload templates and guidelines Create templates and guidelines for running events, Develop a submission page for new ideas on products/services
Conduct Verification Testing Develop donation portal for potential investors, Develop a submission page for new ideas on products/services, Develop a registration page for

organizations to develop custom websites, Develop tracking system, Develop incentive system
Conduct Validation Testing Conduct Verification Testing
Conduct Pilot Testing Conduct Validation Testing
Hold Four Events (in different countries) to Test Site Functionality Conduct Pilot Testing
Obtain Feedback Hold Four Events (in different countries) to Test Site Functionality
Implement Changes Obtain Feedback
Move site to production server Implement Changes
Determine roll out schedule Implement Changes, Move site to production server
Communicate roll out plan to users Determine roll out schedule
Conduct user training Conduct Pilot Testing
Deploy system Communicate roll out plan to users
Determine what support resources are needed Conduct user training, Deploy system
Make appropriate staffing changes Determine what support resources are needed
Determine method that users will attain support Determine what support resources are needed
Determine support process Determine what support resources are needed
Launch support Make appropriate staffing changes, Determine method that users will attain support, Determine support process
Hold formal customer review Launch support
Prepare final report and presentation Hold formal customer review
Deliver final report and presentation Prepare final report and presentation